But group spokespeople said that the latest overruns had been driven by a failure to reach an agreement with steel contractor Hollandia on the upper limit of the cost of steel and labor. Steel prices have been rising, and it is understood that, if a fixed-price contract is not agreed upon, the overruns may rise beyond the revised estimate of euro 111 million ($132 million) outlined yesterday.

While the negotiations are at an advanced stage they remain incomplete, and it is possible that "Multiplex will not conclude a mutually acceptable agreement with Hollandia," said McDonald. He added that Multiplex would attempt to recover shortfalls in income through a series of "claims." Legal action is currently under way against Cleveland Bridge.

The news will increase speculation that Multiplex will be forced into further cut backs of its UK development drive and make further disposals from its euro 6.55 billion ($5.47 billion) UK portfolio.

NOT FOR REPRINT

© Touchpoint Markets, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more inforrmation visit Asset & Logo Licensing.